Navigating to Resource Requests

FOUNDATION > RESOURCE SCHEDULING > MANAGE RESOURCE REQUESTS

Using Resource Requests

Resource Requests are requests made from agents to allocate available company Resources for specific tasks. The availability of Resources depends on the Resource entries generated from Resource Plans. Requests may be directly approved, or created in a 'Pending' Life Cycle State, requiring Approval from authorised personnel.
As Resource Requests are specific to One-Time Services added on Activities, Resources are booked to complete the specific Service, i.e. the installation of hardware. 
The request for the Resources can be done through the Activities Data Entry page or through the Resource Request Data Entry page.

  • Navigate to Resource Requests and explore existing entries via the Summary page
  • Click on the link (Name or Number) of the entry of your interest to enter the Data Entry page and see more detail. 
  • Use the Actions Menu to create a NEW Resource Request or modify (EDIT) an existing one. 
  • Use BACK to return to the Summary page and CANCEL to revert any unwanted changes made to the Resource Request. 
  • Click on ACTIONS to discover other possibilities available for Resource Requests.
  • Click on the Audit Log button to view a log of changes performed on the displayed Resource Requests.

 

Check the Validations & Restrictions Table for a list of available Actions when working with Resource Requests including each Action's related restrictions, validations and a description of its system process.  View the Attributes Table below for a comprehensive description of the Resource Requests fields.  

 

Resource Requests

Validations & Restrictions

ActionValidationsRestrictionsSystem Processing
Create
  • Mandatory Fields:
    • Requested Unit
    • Number of Resources
    • Requested One Time Service
    • From
    • To
    • Life Cycle State
  • Resource Plans must be configured and available in the System,
  • At least one Resource Definition must be configured and 'Active',

A Resource Request is created when a request is submitted. Request can have one of the following Life Cycle States:

  • 'Pending': The Resource is requested but not delegated, and therefore does not affect Resource Availability. i.e. the Resource Plan Entry is still available to be requested by someone else.
  • 'Accepted': The Resource Requested is delegated on the Activity and the Resource Plan Entry is no longer available.

The Life Cycle State of requests is based on the /wiki/spaces/WIP/pages/10008217 that can be set to require confirmation.

Edit
  • Not Applicable
  • Only Resource Requests with a 'Pending' Life Cycle State can be edited
  • Not Applicable
Delete
  • Not Applicable
  • Resource Requests cannot be deleted.
  • Not Applicable
Accept
  • Validates that the Requested Resource Plan Entry is still available.
  • Resource Requests can be accepted only if they are in a 'Pending' state.
  • Not Applicable
Cancel
  • Not Applicable
  • Resource Requests can be cancelled only if they are in one of the following states:
    • 'Pending'
    • 'Accepted'
    • 'Rejected'
  • Not Applicable
Reject
  • Not Applicable
  • Resource Requests can be accepted only if they are in a 'Pending' state
  • Not Applicable

 

Attributes

An * indicates a field is mandatory.

Name

Description

Number

A number which is generated automatically and is used to identify the Resource Request.

Main Information

Requested By Unit

The Unit that is requesting the Resource.

Requested By User

The User that is requesting the Resource.

Description

A description of the Resource Request.

Life Cycle State*

Determines the state of the Resource Request which can be one of the following:

  • Pending
  • Accepted
  • Rejected
  • Cancelled
Request Information
Requested Resources From

Unit*

The Unit that a Resource is requested from.

If the Requested Unit is not defined when creating a new Resource Request, it will be automatically populated once the Requested One-Time Service is selected from the respective tab.

Number of Resources*

The number of required Resources.

Requested Resources For*

Activity

The Activity for which the requested Resource should be provided.

JobThe Job for which the requested Resource should be provided.
ServiceThe One-Time Service that the requested Resource should be provided.

From*

The date and time from which the Resource is Requested to be available.
Set once a Resource Request is saved. 
If more than one slot is selected then 'From' is set to the earliest From Date/Time of all selected Slots. i.e.,

Selected Slots :

01.12.2014 08:00-09:00

01.12.2014 09:00-10:00

From = 01.12.2014 08:00 

To*

The date and time until which the Resource is Requested to be available.

Set once a Resource Request is saved. 
If more than one slot is selected then the 'To' is set to the latest To Date/Time of all selected Slots. i.e.,

Selected Slots :

01.12.2014 08:00-09:00

01.12.2014 09:00-10:00

To = 01.12.2014 10:00 

Requested Resource Plan Entry

Available for Resource Requests that are not yet 'Accepted'

 

Requested Resource Plan Entry

The Resource Plan entry, requested for the Resource Request

Only available for existing Resource Requests

Available Entries (link) 

Allows you to search among available Resource Plan Entries. Click on the link and follow the steps described here.

Available only in Edit Mode

View

Provides information related to the Resource Plan Entry that has been requested

Reserved Resource Plan Entry

Available once Resource Requests are 'Accepted'

 

Reserved Resource Plan Entry

 The Resource Plan entry which was reserved for the Resource Request once it was accepted.
View

Provides information related to the Resource Plan Entry that has been booked.

Log Information
Log DetailsThe standard set of Log Details information available in all entities.

 

Selecting an Available Resource Plan Entry

The process for requesting a Resource through the Resource Requests page or through the Activity page is the same.
Resource Availability
 

  1. Provide the following information and click to SEARCH within the available Resource Plan Entries.
    1. Requested Unit
      If 'Assigned to Unit' is already defined for the Activity, then automatically the Unit is set in the Requested
    2. From Date and To Date (optionally providing the desired hour slots)
      1. From Date: If the Start Date of the Job or Activity is defined and is greater than the current date, then From date is set to Start Date, otherwise is set to the current date.
      2. To Date:  Automatically set to the Estimated Completion Date of the Activity. If not available or Estimated Completion Date of the Job/Activity is greater that the current date then it is set equal to: From date +  7 days

    3. Request Resources, in the Action Details section, is set based on the Number of Resources defined in the Resource Requests Data Entry page.
  2. Taking the following into account, the System searches for available Resource Entries that meet the required criteria:
    1. Requested Unit 
    2. Service
    3. From Date
    4. To Date
  3. Available Resources will be displayed in the SEARCH RESULTS section.
    1. Planned Resources: The number of Resources defined when creating the plan.
    2. Available Resources: The number of Resources that have not yet been booked.

      If the Planned Resources < Available Resources, it means that Overbooking Percentage has been set to be greater than 0 % and (most likely) no Resources have yet been allocated.

      If the Planned Resources > Available Resources, it means that some Resources have already been allocated and thus removed from the available Resources.

  4. Check the select box to the left of the entry you would like to book and click on SELECT.

    Resources from two different entries (two different days) cannot be booked.
    As many slots as necessary can be booked from the same entry (day), but that will be greater or equal to the Minimum Duration, and less than or equal to the Maximum Duration set on the Service when creating a Resource Plan.

Additional Actions for Resource Requests

Actions available for Resource Requests

Accepting Resource Requests

One or multiple Resource Requests can be accepted. On accepting a Resource Request its Life Cycle State is automatically set to 'Accepted' and the Resource Plan entry is reserved against that request, affecting immediately the Resource's availability. 

  1. Navigate to MANAGE Resource REQUESTS.
  2. Search for a single Resource Request with its Life Cycle State set to 'Pending'.
  3. Click on the Number of the request you want to access to go to the Data Entry page.
  4. From the Actions Menu click on ACTIONS > ACCEPT.

Rejecting Resource Requests

One or multiple Resource Requests can be rejected. On rejecting a Resource Request its Life Cycle State is automatically set to 'Rejected' and the Resource availability is not affected.

  1. Navigate to MANAGE Resource REQUESTS.
  2. Search for a single Resource Request with its Life Cycle State set to 'Pending'.
  3. Click on the Number of the request you want to access to go to the Data Entry page.
  4. From the Actions Menu click on ACTIONS > REJECT.

Cancelling Resource Requests

One or multiple Resource Requests can be cancelled. On cancelling a Resource Request its Life Cycle State is automatically set to 'Cancelled' and the Resource availability is not affected.

  1. Navigate to MANAGE Resource REQUESTS.
  2. Search for a single Resource Request with its Life Cycle State set to 'Pending', 'Accepted' or 'Rejected'.
  3. Click on the Number of the request you want to access to go to the Data Entry page.
  4. From the Actions Menu click on ACTIONS > CANCEL.

All actions can be executed for multiple Resource Requests and simultaneously if executed through the Summary page. Select the requests to be processed by checking the Select Box.