  1. Select from the available options according to what you would like to achieve
    1. RUN NOW: Will be executed once, now 
    2. RUN ON SPECIFIC DATE/TIME: Will be executed once, at the date defined
    3. RUN REPEATEDLY: Will be executed, starting and ending at a defined date/time and will be repeated every X UOT where UOT can be from seconds to Years
    4. ADVANCED SCHEDULING: Will be executed, starting and ending at a defined date with powerful repetition options from daily to yearly
  2. RUN NOW

    SCHEDULING SETTINGS - RUN NOW
     

  3. RUN ON SPECIFIC DATE / TIME

    1. Start Process
      1. Click on the calendar select the date and time the run should start being executed. 
        DATE AND TIME SELECTION
      2. Once selected click on DONE
        RUN ON SPECIFIC DATE TIME
  4. RUN REPEATEDLY

    1. Start Process - On a Specific Date
      1. Click on the calendar select the date and time the run should start being executed. 
        DATE AND TIME SELECTIONImage Removed
      2. Once selected click on DONE
    2. OR Start process - After a period of time
      1. Provide how long after current date/time the process should begin
        START PROCESS - AFTER A PERIOD OF TIMEImage Added 
    3. Repeat Process
      1. EVERY: Type a number (INTEGER)
      2. UOT: Select between
        1. Seconds
        2. Minutes
        3. Hours
        4. Days
        5. Weeks
        6. Months
        7. Years
          REPEAT - UOT
    4. End Process
      1. Select between
        1. Never End
        2. On a specific date (define the date)
        3. After a period of time (define period of time)
          END PROCESS 
  5. ADVANCE SCHEDULING

    1. Start Process
      1. Click on the calendar select the date and time the run should start being executed. 
      2. Once selected click on DONE
        ADVANCED SCHEDULING 
    2. Repeat Process
      1. Select between
        1. Daily : Define every how many days 
        2. Weekly: Select specific days of the week 
        3. Monthly:Define every how many months or on a specific day of the month
        4. Yearly: Define a specific date/month or a specific day of a month, such as the 1st Sunday of every January
          ADVANCED SCHEDULING - REPEAT PROCESSImage Added
    3. End Process
      1. Select between
        1. Never End
        2. On a specific date (define the date)
          ADVANCED - END PROCESS